Evaluation of different peat handling systems and Finnish peat equipment suppliers for a Russian Investment bank investing in the cement industry.


New green field cement plant 1,5 Mtpa

  • Participation in the conceptual and pre planning (2006 – 2007)

Leningrad (St Petersburg) area

Rehabilitation and modernization of dry kiln
(2004-2006)

  • 4-stage cyclone pre heater kiln
  • Capacity 800 à 1200 t/d clinker
  • Over all project coordination and engineering from preplanning to implementation (equipment, electrification and automation)


Phase 1




  • New kiln filter (bag), new GCT (gas conditioning tower), new CO, NOx and CH4 sampling and analysing system, new kiln feeding system, new kiln inlet sealing, changes and component improvements of the preheater, renovation and improvements (new static grate) of the kiln grate cooler, new clinker crusher (redundant from Estonia), new electrification, instrumentation and process control system

Phase 2

  • New coal feed and multi purpose burner, IR- pyrometer, kiln dust return to the kiln process

The coordination of all small plant investments (2002 – 2006)

Many plant technical audits in Russia (1994 – 1999)