Ukraine
Khemelsky area (2006-
2011 – 2012 Various pre engineering projects
- New raw meal silo No 2 (10 000 t)
- New cement grinding system (300 t/h)
- Extension of the existing new clinker handling and storing system
Main tasks: technical concept, flow sheet, layout, budget quote etc. comparisons, cost estimate and time schedule. Reporting.
New production line (7500 t/d clinker) various interface project tasks.
- design and project engineering
- Main layout of the new production line
Interface projects 2007 – 2010
- Limestone incomers from quarry- connection to the new system
- Clinker conveying to new circular storage including reject silo
- discharging and conveying to new and old cement grinding department
- Intake and distribution of cement additives (Slag, limestone and gypsum) to the new cement mill (250 t/h)
- Cement conveying and distribution to 8 existing storage silos from the new cement mill considering the pneumatic conveying from the old (12) cement mills
The design manager position in the local project organization 8/2007 – 12/2011
Dnepropetrovsk area
Conversion of two (2) open circuit cement mills to closed circuits (50 – 65 t/h) with new feeders and mill filter to the third mill
- Over all project coordination and engineering from preplanning to implementation (equipment, electrification and automation)